SWDC is a 200,000-square foot, 315-bed male/female state-of-the-art detention centre that opened in 2014. The facility was built using the P3 model of procuring public infrastructure.

As part of the construction team, SWS Detention Group supplied and installed detention hollow metal doors (500+openings), frames, detention hardware, detention specialties, security washroom accessories and dayroom furnishings. The locking system is electro-pneumatic and includes both swing and sliding doors.

Owner – Infrastructure Ontario

P3 Asset Manager – Forum Equity Partners

Architect – NORR

General Contractor – Bondfield Construction

Detention Equipment Contractor – SWS Detention Group, Inc.

Detention Hollow Metal – Trussbilt

Detention Hardware – Southern Folger

Detention Furnishings - Norix